The Job

This project involved a full decoration refurbishment, both internally and externally. The process was as follows:

  • Provisional jet wash/clean of cladding, including all internal areas (stripping existing plastisol)
  • Cladding was prayed with a specialist coating, giving the client a 10 year guarantee. There was almost 2000sqm of cladding on this project.
  • Breezeblocks & Internal Beams were painted internally
  • Roller Shutters were also painted to complete the final look.

This project took just under 2 months to complete. Our Client was very happy with the final look and has certainly increased the value of their property.